Enbridge ordered to pay $3 million for Line 3 groundwater leak

Minnesota regulators have ordered Enbridge to pay more than $3 million for allegedly violating state environmental law by piercing a groundwater aquifer during construction of the Line 3 oil pipeline replacement.

Aug 30, 2021: Dozens of environmental and Indigenous rights advocates are facing charges after being arrested in Minnesota over the weekend. They were protesting outside the governor’s mansion in opposition of Line 3 pipeline. Tara Houska, a tribal attorney and founder of Giniw Collective, joined CBSN to discuss the significance of the movement against the oil pipeline project.

The state Department of Natural Resources said Enbridge, while working near Clearbrook in January, dug too deeply into the ground and pierced an artesian aquifer, which resulted in a 24 million gallon groundwater leak.

“Enbridge’s actions are a clear violation of state law, and also of the public trust,” said Barb Naramore, DNR deputy commissioner. “That is why we are using all of the tools in our authority to address the situation.”

Jul 23, 2021: Just Out of Jail, Winona LaDuke Decries Militarized Crackdown on Enbridge Line 3 Pipeline Protests

Enbridge said in a statement Friday that it was reviewing the DNR’s order and would work with the agency on a resolution.

“Enbridge has been working with the DNR since June to provide the required site information and approval of a corrective action plan which is currently being implemented,” the Calgary, Alberta-based company said. “We share a strong desire to protect Minnesota waters and the environment and we are committed to restoration.”

It wasn’t until mid-June that the DNR discovered something was wrong after speaking to independent construction monitors who had observed water pooling in the pipeline trench near Clearbrook.

May 12, 2021: Enbridge said it will defy Line 5 shutdown order as Gov. Whitmer threatens more action

The DNR has ordered Enbridge to put $2.7 million into escrow for restoration and damage to nearby wetlands. Enbridge is also required to pay $300,000 to mitigate the lost groundwater and $250,000 for long-term monitoring of the wetlands.

Enbridge’s 340-mile (547-kilometer) Line 3 replacement pipeline will carry Canadian crude across northern Minnesota to the company’s terminal in Superior, Wisconsin. The pipeline, opposed by environmental groups and some Ojibwe tribes, is nearly complete. The project is replacing a deteriorating line built in the 1960s that can only run at half capacity.

https://www.pbs.org/newshour/nation/enbridge-ordered-to-pay-3-million-for-line-3-groundwater-leak

Advertisement

Published by amongthefray

News with a historical perspective. Fighting against misinformation, hate, and revisionist history.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: